2 Tasks – Project Dependencies Explained
Part of the process of building a project schedule involves breaking down the work into smaller activities (the Work Breakdown Structure) and then sequencing the activities. When you sequence the activities you should make sure that every activity is related to at least one other activity. In many cases, the relationships will involve two or more activities.